U.S. AI Data Center Development Reaccelerates in January as Multi-Gigawatt Projects Advance Nationwide

Data Center KPIs as of February 13, 2026

Data Center KPIs 20260213

Aterio Logo

Aterio Logo

January saw renewed construction, permitting, and power-linked site activity as Microsoft, Amazon, Crusoe, and TeraWulf advanced major projects nationwide.

AI-driven demand continues to expand geographically, and tracking permitting, power access, and construction progress provides a clearer view of where capacity is forming next.”
— Sergio Toro, CEO, Aterio
VANCOUVER, BRITISH COLUMBIA, CANADA, February 17, 2026 /EINPresswire.com/ -- Aterio, a provider of continuously updated U.S. data center intelligence, released its February 2026 US Datacenter Monthly industry update. The report summarizes major development activity observed during January 2026 across the United States, including multi-building campus approvals, construction mobilization, new air and building permits, power-linked site acquisitions, and execution updates.

Aterio publishes monthly industry updates informed by its daily-updated subscription dataset, which tracks every active, under-construction, and announced U.S. data center project nationwide.

LARGE-SCALE AI CAMPUS CONSTRUCTION

Microsoft received approval in Mount Pleasant, Wisconsin for a 15-building data center campus across two adjacent sites, expanding well beyond its earlier six-building concept and diverging from its typical Fairwater layout design.

Crusoe filed new permits for Buildings 5 and 6 at its Project Goodnight campus in Armstrong County, Texas. Recent satellite imagery confirms construction activity beginning on-site.

Crusoe’s five-building Project Jade campus in Laramie County, Wyoming is showing post-approval mobilization. Aterio’s latest satellite review identified construction activity near the adjacent substation and early ground movement across portions of the site.

CAPACITY EXPANSION AND SITE ACQUISITION

TeraWulf acquired two new development sites in Hawesville, Kentucky (480 MW) and at Maryland’s Morgantown Generating Station (210 MW), adding approximately 1.5 GW of power capacity to its broader development pipeline.

Google has been identified as the end-user behind two proposed projects: A ~500,000 sq ft campus in Scioto County, Ohio and a ~300,000 sq ft facility at the Port of Little Rock, Arkansas. Both projects reinforce Google’s continued regional expansion strategy.

REZONING AND EARLY-STAGE DEVELOPMENT FILINGS

Forsyth City Council voted 5–1 to grant a conditional use permit for the 1,600-acre Forsyth Technology Campus, where Trammell Crow Company and H&H Timberlands plan a 21-building data center campus. Total power capacity has not yet been disclosed.

Atlas Development submitted an application for Project Bus in Temple, Texas, proposing up to 12 data center buildings and two on-site substations.

Nebius filed a building permit on January 29, 2026 for its data center campus in Birmingham, Alabama, covering a 79-acre site.

INCREMENTAL CAMPUS EXPANSION

Through an air permit filing, Aterio identified a new Amazon campus near Reno, Nevada outlining a nine-building layout, each with 38 generators rated at 3.5 MW, with four buildings already under construction.

PROJECT STATUS CHANGES AND EXECUTION UPDATES

Aterio’s satellite analysis indicates a Q4 execution delay at Amazon’s Project Rainier. Approximately 260 MW of incremental capacity appears activation-ready versus the ~520 MW initially implied, suggesting a slower-than-anticipated ramp.

MARKET OUTLOOK

January reflected renewed activity following typical year-end moderation, with development momentum distributed across Wisconsin, Texas, Nevada, Kentucky, Wyoming, Alabama, Arkansas, and Ohio. Construction mobilization, zoning approvals, and power-backed site acquisitions suggest continued geographic diversification beyond traditional hyperscale hubs.

As 2026 progresses, monitoring substation-linked projects, phased campus builds, and execution timelines will remain critical to understanding the pace and distribution of U.S. AI-driven infrastructure expansion.

ABOUT ATERIO

Aterio provides real-time, facility-level intelligence on U.S. data center development, AI-driven power demand, and digital infrastructure growth. Its continuously updated subscription dataset tracks every active, under-construction, and announced data center project across the United States.

Learn more at https://www.aterio.io

Aterio Data Team
Aterio
+1 604-368-7373
data@aterio.io
Visit us on social media:
LinkedIn
Other

Legal Disclaimer:

EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.

Share us

on your social networks:
AGPs

Get the latest news on this topic.

SIGN UP FOR FREE TODAY

No Thanks

By signing to this email alert, you
agree to our Terms & Conditions